How do companies execute a turn-key project??
Companies specialized in this field have an extensive
database from all manufacturers, and request a quote from
those manufacturers for their projects. Manufacturers will
give a quote and most of those companies have their own with
the local agent. For those reasons we were encouraged to go
down this path because we feel that we can do a better job
and give a high quality after sales services.
OUR STRATEGY
We did an extensive research and went into joint venture
with two very reputable construction and Consultancy
Companies (KHAKI and ASSOCIATES) & (ARKONSULT
ENGINEERING CONSULTANTS) Those two companies are
considered as giants in their resources and capabilities, and
have executed numerous projects in the UAE and in Iraq as
well
WILL WE DO A BETTER JOB??? WHY???
We felt that we have an edge over all other companies for
the following reasons;
1- We will be installing equipment we are familiar with;
our engineers have been trained to install them.
2- Our prices will be more competitive because we are
getting the equipment from the companies we
represent direct without a mediator.
3- Our services and presence in the hospitals to do the
installations and maintenance will have more personal
touch because our technical staff over the years has
established a very healthy working relationship with
all the technical staff of the ministry of health.
4- We felt that hospital managers and technical staff
will have an easier task when they have one body to
contact in case of emergency, instead of depending
on different agents.
I. DESIGN PHASE
A. CONCEPTUAL DESIGN
FORM FOLLOWS FUNCTION
WHAT DO YOU WANT TO DO & WHERE?
Factors influencing design
Medical and Surgical disciplines required
Document describes Overall departments operational work
flow
Description of activities in each room
Room relationships
Staffing
Schedule of Accommodation
B. PRELIMINARY DETAILED DESIGN
Following approval of previous conceptual design phase the
design architect team will supply
1- 1:200 FLOOR PLAN
2- 1st ISSUE ROOM DATA SHEETS
C. DETAILED DESIGN DOCUMENTS
Following the approval of previous preliminary design
architect, civil engineering and medical planning staff will
supply totally integrated drawings of engineering with
medical equipment and furniture components.
II. EXECUTION PHASE
III. SUPPLY PHASE